Phase 1 building work started on 9th April 2018. During the course of this year, the following premises on the High Street will have new facades installed:
72, 72A, 83, 89, 109, 115 & 117
Images of these properties as they looked on 30th March 2018 are shown below.
The indicative schedule for Phase 2 will be:
- January 2018 to July 2018
- Detailed design, consultation with owners and shopkeepers, negotiation on legal agreements, and submission of planning applications
- September 2018 to October 2018
- Carry out tender processes
- January 2019 to June 2019
- Carry out the phase 2 contract