Please note: Work on this aspect of the project is currently suspended because of the coronavirus restrictions.
Phase 2
The programme for this phase is:
- September 2018 to July 2019
- Detailed design
- Consultation with owners and shopkeepers
- Negotiation on legal agreements
- Submission of planning applications
- July 2019 to December 2019
- Carry out Tender and related processes
- 2020
- Finalize Agreements and carry out the phase 2 contract
Phase 1
The building work started on 9th April 2018. During the course of the year, the following premises on the High Street have had new facades installed:
72, 72A, 79, 83, 89, 103, 109, 115 & 117
Images of these properties as they looked on 30th March 2018 are shown below.
Images of these properties as they looked after completion of the work are shown below.