This gives an indication of the project’s complexity and the adverse impact of the coronavirus pandemic. These entries will be further condensed at a later date.
- 2011
- Skelton Villages Civic Pride is formed
- 2012
- Skelton Villages Civic Pride undertakes first summer planting of barrels and pole baskets
- 2013
- First application made unsuccessfully to the Heritage Lottery Fund
- 2014
- “Round 1” application made to the Heritage Lottery Fund for a Townscape Heritage project for Skelton
- 2015
- February
- Heritage Lottery Fund approves a Round 1 Development Grant of £69,200 to work up proposals for the Skelton Townscape Heritage project
- May
- Project manager starts work
- July
- Physical survey and heritage audit
- September & October
- Design consultants appointed and outline proposals prepared
- 26th October
- Public consultation event
- December
- Design review with the Heritage Lottery Fund
- February
- 2016
- January & February
- Design & cost review; final design review with the Heritage Lottery Fund
- March
- Round 2 bid submitted to the Heritage Lottery Fund
- June
- Heritage Lottery Fund approves our proposals
- July
- “Permission to Start” issued by the Heritage Lottery Fund
- September
- Activity 4: “Snapshot in Time” started
- Tees Archaeology appointed to undertake Activity 1: Boroughgate Archaeology
- October
- Public realm design consultant appointed
- November
- 1st phase of Activity 1: Boroughgate Archaeology
- Public realm detailed design started
- December
- Building design consultant appointed
- Cost consultant appointed
- Start of owner consultation
- January & February
- 2017
- January
- Carry out internal survey of Phase 1 shops
- Start of detailed building design
- February
- Tender public realm works
- February to March
- Detailed building design
- April
- Design & legal consultation with Phase 1 shop-owners
- May
- Activity 1: Boroughgate Archaeology: Earthworks survey
- Public realm works contract starts on site
- Summer
- Complete public realm works
- Undertake 2nd tranche, Activity 4: “Snapshot in Time”
- Further design consultation with first phase owner
- Autumn
- Undertake first part of Activity 8: Mosaic trail
- Commence Activity 3: Recorded memories
- Tender first phase building work
- Winter
- First phase building works – Tenders returned, evaluated and contractor selected
- January
- 2018
- Spring
- Commence first phase building works
- Commence Activity 3: Recorded memories
- Design & tender second phase building works
- Summer
- Design second phase building works
- Undertake Activity 1: Boroughgate Archaeology excavation
- Continue Activity 3: Recorded memories
- Undertake Activity 6: Medieval re-enactment day
- Autumn
- Continue Activity 3: Recorded memories
- Undertake 3rd tranche, Activity 4: “Snapshot in Time”
- Commence Activity 5: research for project history
- Commence installing second phase of Activity 8: Mosaic trail
- Spring
- 2019
- Complete 2nd year of Project Evaluation
- Complete extended Phase 1 building works
- Continue Activity 3: Recorded memories
- Design and install Activity 2: Interpretation panels at Boroughgate
- Design and tender second phase building works
- Complete installing second phase of Activity 8: Mosaic trail
- Undertake 4th tranche of Activity 4: Snapshot in time
- Complete work on Activity 5: Project history – and prepare for publication
- Activity 8: Mosaic trail – Prepare and publish a guide leaflet
- 2020
- Coronavirus pandemic begins. All work on project ceases.
- 2021
- Post-pandemic economic uncertainty means several properties withdraw
- Undertake second phase building works on remaining properties
- Complete and archive Activity 3: Recorded memories
- Publish Activity 5: Skelton Revealed was published in February
- Complete project-end evaluation