The Timetable

This gives an indication of the project’s complexity and the adverse impact of the coronavirus pandemic. These entries will be further condensed at a later date.

  • 2011
    • Skelton Villages Civic Pride is formed
  • 2012
    • Skelton Villages Civic Pride undertakes first summer planting of barrels and pole baskets
  • 2013
    • First application made unsuccessfully to the Heritage Lottery Fund
  • 2014
    • “Round 1” application made to the Heritage Lottery Fund for a Townscape Heritage project for Skelton
  • 2015
    • February
      • Heritage Lottery Fund approves a Round 1 Development Grant of £69,200 to work up proposals for the Skelton Townscape Heritage project
    • May
      • Project manager starts work
    • July
      • Physical survey and heritage audit
    • September & October
      • Design consultants appointed and outline proposals prepared
    • 26th October
      • Public consultation event
    • December
      • Design review with the Heritage Lottery Fund
  • 2016               
    • January & February
      • Design & cost review; final design review with the Heritage Lottery Fund
    • March
      • Round 2 bid submitted to the Heritage Lottery Fund
    • June
      • Heritage Lottery Fund approves our proposals
    • July
      • “Permission to Start” issued by the Heritage Lottery Fund
    • September
    • October
      • Public realm design consultant appointed
    • November
    • December
      • Building design consultant appointed
      • Cost consultant appointed
      • Start of owner consultation
  • 2017
    • January
      • Carry out internal survey of Phase 1 shops
      • Start of detailed building design
    • February
      • Tender public realm works
    • February to March
      • Detailed building design
    • April
      • Design & legal consultation with Phase 1 shop-owners
    • May
      • Activity 1: Boroughgate Archaeology: Earthworks survey
      • Public realm works contract starts on site
    • Summer
      • Complete public realm works
      • Undertake 2nd tranche, Activity 4: “Snapshot in Time”
      • Further design consultation with first phase owner
    • Autumn
      • Undertake first part of Activity 8: Mosaic trail
      • Commence Activity 3: Recorded memories
      • Tender first phase building work
    • Winter
      • First phase building works – Tenders returned, evaluated and contractor selected
  • 2018
    • Spring
      • Commence first phase building works
      • Commence Activity 3: Recorded memories
      • Design & tender second phase building works
    • Summer
      • Design second phase building works
      • Undertake Activity 1: Boroughgate Archaeology excavation
      • Continue Activity 3: Recorded memories
      • Undertake Activity 6: Medieval re-enactment day
    • Autumn
      • Continue Activity 3: Recorded memories
      • Undertake 3rd tranche, Activity 4: “Snapshot in Time”
      • Commence Activity 5: research for project history
      • Commence installing second phase of Activity 8: Mosaic trail
  • 2019
    • Complete 2nd year of Project Evaluation
    • Complete extended Phase 1 building works
    • Continue Activity 3: Recorded memories
    • Design and install Activity 2: Interpretation panels at Boroughgate
    • Design and tender second phase building works
    • Complete installing second phase of Activity 8: Mosaic trail
    • Undertake 4th tranche of Activity 4: Snapshot in time
    • Complete work on Activity 5: Project history – and prepare for publication
    • Activity 8: Mosaic trail – Prepare and publish a guide leaflet
  • 2020
    • Coronavirus pandemic begins. All work on project ceases.
  • 2021
    • Post-pandemic economic uncertainty means several properties withdraw
    • Undertake second phase building works on remaining properties
    • Complete and archive Activity 3: Recorded memories
    • Publish Activity 5: Skelton Revealed was published in February
    • Complete project-end evaluation